Interlock Stone Laying at Katunayaka Airport & BOI Central Road
Location: Katunayaka Airport & BOI Central Road
Type of Interlock Stone Used: Cobbel Red
Strength: 40 N/mm²
Project Details
1. Preparation:
Our first step involved ensuring a solid foundation. Quarry dust was applied in two trenches on a well-pressed ABC layer of four trenches. This provided a stable base for the interlock bricks.
2. Laying the Interlock Stones:
The interlock bricks, supplied by RDA, were carefully spread on the prepared base. Our team ensured precise alignment and spacing to achieve a smooth and durable finish.
3. Installing the Curbstone:
Before laying the carpet for the road, we installed the curbstone. This crucial step provided a defined edge and maintained the integrity of the interlock stone layout.
Project Timeline
- Date of Commencement: 05-02-2020
- Date of Completion: 16-02-2020
- Total Time Taken: 12 days
Our dedicated team worked diligently to complete the project within the stipulated timeframe, ensuring high standards of quality and efficiency.
Results
The completed project not only enhances the aesthetic appeal of Katunayaka Airport & BOI Central Road but also provides a durable and robust surface capable of withstanding heavy traffic. Our Cobbel Red interlock stones are designed for longevity and resilience, making them an ideal choice for such critical infrastructure projects.
Conclusion
At Offer Paving Construction, we take pride in delivering top-notch services and high-quality materials. This project at Katunayaka Airport & BOI Central Road stands as a testament to our commitment to excellence. We look forward to undertaking more such projects and continuing to provide our clients with the best paving solutions.